WAY PAST habagat and under
the sweltering heat of the October sun, sections of two flood control
structures in Arayat collapsed over the weekend, raising anew the spectre of
the forever collapsing Candating flood control system in the mind of the
terrified folk.
Mid-September’s torrential
rains and the raging waters of the Pampanga River battering the flood control project
in Barangay San Mateo are said to have caused erosion of the embankment and the
partial collapse of its sheet piles on a rainless, floodless, dry and humid Oct.
2.
Barangay San Mateo flood control project. CLMA-Pampanga
Arayat Mayor Jeffrey Luriz
promptly calling the Department of Public Works and Highways for urgent action
as no less than 20 houses were in danger of collapse too if no immediate
intervention is implemented.

The following as-dry and
sunny day, a section of the flood control system in Barangay Lacquios caved in
with its sheet piles tilted riverway.
The skewed sheet piles
unraveling; the story of Candating there rehappening. Recapped, thus:
Collapsed in August 2024,
its rehabilitation far from completed when inundated – at the point of complete
collapse – by the monsoons in July-August 2025.
Named by Sen. Ping Lacson
as the “face of failed flood control projects” immediately before the Senate
investigations.

Jointly investigated in
September 2025 by the Independent Commission for Infrastructure and Public
Works Secretary Vince Dizon, who did not contain his anger over “the patently
substandard” construction and extracted from the project contractor, Edgardo Sagum,
proprietor of Eddmari Construction and Trading Corp., the vow to repair the
damage soonest and ablest –
Only to collapse again on
Jan. 23, 2026, damaging at least 16 homes and endangering more along the
downstream of Pampanga River.
Indeed, those sheet piles:
Dizon confronting Sagum. Contributed photo
“Dapat naman (bunutin ang sheet piles), gusto nating malaman kung talagang 36 meters. That’s practically 10-storey building,” Dizon, at Candating September last year, in an early show of his now- patented “init-ulo” mode berating Sagum. “Dalawa lang ang problema…either may problema sa paggawa mo or yung design mali. Ganun lang ‘yun. So aalamin natin yan. Kailangan ito ipa-assess yung design nito kung tama ba o hindi.”
No, the sheet piles were never pulled out. After some media-covered perfunctory extraction tries, Eddmari Construction – sans any reported design re-assessment – just went on with its way of “repairing” the damage to “completion ahead” of its promised last-week-of-November-2025.
Rehabilitation completed ahead of schedule, Eddmari claims. GNN-44
And that was that. Eddmari going off media radar; Dizon’s thermal temper channeled to myriad infra failures across the archipelago.
Still, impacted in its
very image, the “face of failed flood control projects” – no thanks to Lacson,
the senator – Eddmari Construction shall bear to its eternal shame.
To be fair, the damaged
flood-mitigating projects at issue have different contractors: a Royal Crown
Monarch Construction in Laquios, according to the barangay folk; Sto. Cristo
Construction & Trading in San Mateo, if we go by the informational
tarpaulin of the DPWH at the site.
Sto. Cristo Construction.
At once, alarm bells ring; red flags, instantaneously rising.
Per https://sumbongsapangulo.ph/,
Sto. Cristo Construction & Trading is the top contractor of flood control
projects in Pampanga with a total of P1.713 billion. But a miniscule is the Arayat-Phase
2 San Mateo project at P91.095 million.
In Candaba alone, Sto
Cristo Construction wangled P1.157 billion for projects at the Malasik River,
and another P341.678 million for Maasim River.
Former Candaba Mayor
Jerry Pelayo takes flood control woes to NBI. Philstar
Only last month, former Candaba Mayor Jerry Pelayo and a legal counsel representing Candaba residents filed with the National Bureau of Investigation’s Organized and Transnational Crimes Division a formal complaint over alleged irregular spending and substandard construction works tied to Sto. Cristo Construction & Trading and Globalcrete Builders, Inc. in alleged collusion with Candaba Mayor Rene Maglanque and former officers of the DPWH.
With the damaged
embankment in Laquios, especially in San Mateo, connecting the dots may show an
even bigger face of failed flood control projects beyond Arayat.